Project Goals
- Feasibility Study and Conceptual Level Design to inform decision on new RWPS No. 4
- Evaluate potential locations for a new RWPS No. 4
- Target a capacity of approximately 350 MGD with an intake at Elev. 451
- Identify options to provide connection to all four Wylie WTPs
- Evaluate future need for RWPS No. 1 and No. 2
Current Raw Water Pumping from Lavon Lake:
| Current Raw Water Pumping from Lavon Lake |
|---|
| RWPS | Capacity |
| Nos. 1 & 2 | 285 MGD |
| No. 3 | 537 MGD |
All three current pump stations access lake levels between Elev. 461 and Elev. 467. These current capacities and intake levels do not allow for full use of the water right from Lavon Lake.